IE Project Profiles

Baxter Healthcare

Project Details

Project Name


Baxter Healthcare

Project Size


2,000m²

Project Value


€1,5 million

Project Duration


6 months

Cleanroom Classification


ISO 8
Project Overview
Baxter Healthcare

Baxter

This €900k project was completed in a live plant and included rooms of various heights up to 6.0m. The interlocking of doorsets on this project was particularly challenging due to the fact that there were hinged GRP, sliding GRP and rapid roll doors interlocked together.

Provided by Asgard

Products & Services

Ceilings


1,600m² of fully flush long-span walk-on plank ceiling panels.

Partitions


2,000m² of metal faced fully flush FM approved panelling 50mm thick.

Doorsets


Provision of approx 10 GRP doorsets, 2 sliding GRP doors and 5 rapid roll doors.

Structural


Design, supply and installation of a subgrid structure above entire ceiling including integrated handrails to the perimeter.

Furniture


Design, manufacture and installation of stainless steel step over bench.

Interlocking


Design, supply, installation and commissioning of interlocking to 8 doorsets including a 5 door arrangement.

HVAC


Cleanroom panelled low-level extract ducts.