GSK Our Clients

Project Name

GSK Patch

Project Location

Dungarvan,
Waterford,
Ireland

Project Size

1,500 m²

Project Value

€1 million

Project Duration

4 months

Client

DJ Fitzgibbon & Company Ltd.

Architect

DJF Engineering

Engineer

DJF Engineering

Main Contractor

Sisk

Design completed using

Auto CAD

Cleanroom Classification

BSL 2
ISO 5-8

GSK

Patch, BSL 2 & ISO 5-8

Asgard completed the design, supply and installation of this 1,500m² Cleanroom, which included aluminium rapid roller doors, hermetically sealed sliding doors, aluminium honeycomb walk on ceilings and walls. Cleanroom Envelope construction was completed in a very fast twelve week period from commencement to meet clients requirements.

Products & Services Provided by Asgard in this Project

Ceilings

1,500m² of aluminium honeycomb walk-on ceiling panels.

Electrical

Design, supply and installation of recessed stainless steel service panels, automation of sliding and rapid roller doors and their interlocking.

Partitions

2,000m² of flush metal faced panelling system 50mm thick.

Interlocking

Design, supply, installation and commissioning of interlocking systems.

Doorsets

Provision of approx 30 doors including rapid action doors, hermetically sealed sliders, and various hinged doorsets.