Contract Summary
In March 2009, Asgard completed the design, supply and installation of
this €3million 4,000m2 cleanroom fit out, which
included the high specification cleanroom envelope, with Electrical
elements, HVAC grilles, Structural steel elements, etc.
Project design was carried out in full 3D.
Asgard won the award on site for
the contractor of the month during the construction of this project.
Scope of works
• HVAC – Design, supply and
installation of low level return airwalls, safe change filter housings,
supply grilles, pressure Indicative photograph Indicative photograph
differential monitoring..
•
Electrical - Design, supply and installation of all stainless steel
service panels, sockets and switches, automation of rapid roller,
sliding and hinged doors and thier interlocking.
•Ceilings – 4,000m2 of aluminium
grid with approx 500m2 of panelled bulkheads.
• Partitions – 4,000m2 of flush
metal faced fully flush panelling system 50mm thick.
• Doorsets – Provision of approx
10 rapid action doors, 30 heremetic sliders, and 30 fully flush hinged
doorsets.
• Furniture – Design,
manufacture and installation of stainless steel furniture for change
rooms, Phenolic resin laboratory
furniture, stainless steel wall mounted and floor installed bump rails.
Cleanroom telephones, etc etc
|