Medtronic, Galway, Ireland

Contract Summary

This € 2,000,000 project included steel support structure within the building, plenum top to support AHU’s, interior walls and aluminium ceiling system to a 2,500m2 ISO Class 7 cleanroom.

Scope of works

  • Plenum – 2,500m2 of fully flush long-span walk-on plenum panels
  • Ceilings – 2,500m2 of aluminium grid with pre-coated metal tiles
  • Partitions – 3,000m2 of metal faced fully flush FM approved panelling 50mm thick
  • Doorsets – Provision of approx 45 fire rated and non rated doorsets
  • Interlocking –Design, supply, installation and commissioning of interlocking to 14 doorsets
  • Furniture – Design, manufacture and installation of recessed notice boards, magnehelic gauge panels, etc
  • Structural – Design, supply and installation of a steel support structure which supports all of the AHU’s, M+E services, plenum and ceiling system
  • HVAC – Low level air extract