Contract Summary
In January 2008, Asgard
completed the design, supply and installation of this 2,000m2 cleanroom
over four levels, which
included the high specification cleanroom envelope, with some
Electrical elements, HVAC grilles, Structural elements, and fire
rated walls to lift shafts. Cleanroom envelope construction was
completed in a very fast four month period from commencement
of fit out.
Scope of works
•
Electrical -
Design, supply and installation of recessed stainless steel service
panels, automation of sliding and hinged doors and
their interlocking.
•Ceilings – 2,000m2 of FM walk
on ceiling panels.
• Partitions – 4,000m2 of flush
metal faced fully flush panelling system 50mm thick
•
Doorsets – Provision of approx 70 doors including rapid action doors,
harmetically sealed sliders, and various hinged doorsets.
• Interlocking – Design, supply,
installation and commissioning of interlocking systems.
• Furniture – Design,
manufacture and installation of various items of stainless steel
furniture.
|